R - Painting

Project Account and Cost Code for Painting


Stem subRestDetailLevelUoMDescription
R     1   Painting
           
R*     2   Painting Group
RA     2 M2 Painting of Equipment A/M/T/H
RP     2 M2 Painting of Equipment P/G
RF     2 M2 Painting of Storage Tanks
RC     2 M Painting of Piping
RD     2 M2 Painting of Structural Steel
RY     2 M2 Misc. Painting
           
RA *   3   Painting Location
RA F   3 M2 Field
RA S   3 M2 Shop
           
RA _*   4   Equipment Group
RA _A   4 M2 Towers
RA _M   4 M2 Vessels
RA _T   4 M2 Exchangers
RA _H   4 M2 Heaters
           
RA __*   5   Number of Coats
RA __1   5 M2 1 Coat
RA __2   5 M2 2 Coats
RA __3   5 M2 3 Coats
RA __4   5 M2 4 Coats
RA ___*   6   Surface Preparation
RA ___A   6 M2 Degreasing & Touch Up
RA ___B   6 M2 Wirebrushing
RA ___C   6 M2 Blast Cleaning Sa2
RA ___D   6 M2 Blast Cleaning Sa2.5
RA ___E   6 M2 Blast Cleaning Sa3
RA   ___*** 7   Layer Thickness (micron)
RA   ___... 7 M2 - any number -
           
RA ____*   8   Paint Material
RA ____1   8 M2 Alkyd
RA ____2   8 M2 Chloor Rubber
RA ____3   8 M2 Epoxy
RA ____4   8 M2 High Built Epoxy
           
RA _____*   9   Application Method
RA _____1   9 M2 Brushing
RA _____2   9 M2 Spraying
           
RP *   3   Painting Location
RP F   3 M2 Field
RP S   3 M2 Shop
           
RP _*   4   Type of Equipment
RP _P   4 M2 Pumps & Compressors
RP _G   4 M2 Special Equipment
           
RP __*   5   Number of Coats
RP __1   5 M2 1 Coat
RP __2   5 M2 2 Coats
RP __3   5 M2 3 Coats
RP __4   5 M2 4 Coats
RP ___*   5   Surface Preparation
RP ___A   5 M2 Degreasing & Touch Up
RP ___B   5 M2 Wirebrushing
RP ___C   5 M2 Blast Cleaning Sa2
RP ___D   5 M2 Blast Cleaning Sa2.5
RP ___E   5 M2 Blast Cleaning Sa3

Stem subRestDetailLevelUoMDescription
           
RP ____*   5   Paint Material
RP ____1   5 M2 Alkyd
RP ____2   5 M2 Chloor Rubber
RP ____3   5 M2 Epoxy
RP ____4   5 M2 High Built Epoxy
           
RP _____*   5   Application Method
RP _____1   5 M2 Brushing
RP _____2   5 M2 Spraying
           
RP   ___*** 6   Layer Thickness (micron)
RP   ___... 6 M2 - any number -
           
           
RF *   3   Painting Location
RF F   3 M2 Field
RF S   3 M2 Shop
           
RF _*   4   Painting Surface
RF _E   4 M2 External
RF _I   4 M2 Internal
           
RF __*   5   Number of Coats
RF __1   5 M2 1 Coat
RF __2   5 M2 2 Coats
RF __3   5 M2 3 Coats
RF __4   5 M2 4 Coats
RF ___*   5   Surface Preparation
RF ___A   5 M2 Degreasing & Touch Up
RF ___B   5 M2 Wirebrushing
RF ___C   5 M2 Blast Cleaning Sa2
RF ___D   5 M2 Blast Cleaning Sa2.5
RF ___E   5 M2 Blast Cleaning Sa3
RF ____*   5   Paint Material
RF ____1   5 M2 Alkyd
RF ____2   5 M2 Chloor Rubber
RF ____3   5 M2 Epoxy
RF ____4   5 M2 High Built Epoxy
           
RF _____*   5   Application Method
RF _____1   5 M2 Brushing
RF _____2   5 M2 Spraying
           
RF   ___*** 6   Layer Thickness (micron)
RF   ___... 6 M2 - any number -
           
RC *   3   Painting Location
RC F   3 M Field/Non Insulated
RC S   3 M Shop
RC N   3 M Field/Insulated
           
RC __*   4   Number of Coats
RC __1   4 M2 1 Coat
RC __2   4 M2 2 Coats
RC __3   4 M2 3 Coats
RC __4   4 M2 4 Coats
           
RC ___*   5   Surface Preparation
RC ___A   5 M Degreasing & Touch Up
RC ___B   5 M Wirebrushing
RC ___C   5 M Blast Cleaning Sa2
RC ___D   5 M Blast Cleaning Sa2.5
RC ___E   5 M Blast Cleaning Sa3

Stem subRestDetailLevelUoMDescription
           
RC _*   6   Piping Component
RC _B   6 EA Fittings
RC _F   6 EA Flanges
RC _M   6 EA Manifolds
RC _P   6 M Pipe
RC _V   6 EA Valves
RC _X   6 EA Piping
RC   * 7   Size Group
RC   ** 8   Size
           
RC   1 7   < 2"
RC   10 8   Small Bore
RC   11 8   1/8"
RC   12 8   0.25"
RC   13 8   3/8"
RC   14 8   0.5"
RC   15 8   5/8"
RC   16 8   0.75"
RC   17 8   1"
RC   18 8   1.25"
RC   19 8   1.5"
           
RC   2 7   2- 6"
RC   20 8   Medium Bore
RC   21 8   2"
RC   22 8   2.5"
RC   23 8   3"
RC   24 8   4"
RC   25 8   5"
RC   26 8   6"
           
RC   3 7   8-12"
RC   30 8   Large Bore
RC   31 8   8"
RC   32 8   10"
RC   33 8   12"
           
RC   4 7   14-24"
RC   40 8   LB4
RC   41 8   14"
RC   42 8   16"
RC   43 8   18"
RC   44 8   20"
RC   45 8   22"
RC   46 8   24"
           
RC   5 7   26-36"
RC   50 8   LB5
RC   51 8   26"
RC   52 8   28"
RC   53 8   30"
RC   54 8   32"
RC   55 8   34"
RC   56 8   36"
           
RC   6 7   38-48"
RC   60 8   LB6
RC   61 8   38"
RC   62 8   40"
RC   63 8   42"
RC   64 8   44"
RC   65 8   46"
RC   66 8   48"

Stem subRestDetailLevelUoMDescription
           
RC   7 7   >48"
RC   70 8   LB7
RC   71 8   52"
RC   72 8   54"
RC   73 8   56"
RC   74 8   58"
RC   75 8   60"
RC   76 8   64"
RC   77 8   68"
           
RC ____*   9   Paint Material
RC ____1   9 M Alkyd
RC ____2   9 M Chloor Rubber
RC ____3   9 M Epoxy
RC ____4   9 M High Built Epoxy
           
RC   ___*** 10   Layer Thickness (micron)
RC   ___... 10 M - any number -
           
RC _____*   11   Application Method
RC _____1   11 M Brushing
RC _____2   11 M Spraying
           
RD *   3   Painting Location
RD F   3 M2 Field
RD S   3 M2 Shop
           
RD _*   4   Steel Category
RD _A   4 M2 Members < 22 kg/M
RD _B   4 M2 Members 22- 70kg/M
RD _C   4 M2 Members 70-120kg/M
RD _D   4 M2 Members >120 kg/M
RD _F   4 M2 Flooring
RD _H   4 M2 Handrail
RD _L   4 M2 Ladders with Cage
RD _S   4 M2 Pipesupports
           
RD __*   5   Number of Coats
RD __1   5 M2 1 Coat
RD __2   5 M2 2 Coats
RD __3   5 M2 3 Coats
RD __4   5 M2 4 Coats
RD ___*   5   Surface Preparation
RD ___A   5 M2 Degreasing & Touch Up
RD ___B   5 M2 Wirebrushing
RD ___C   5 M2 Blast Cleaning Sa2
RD ___D   5 M2 Blast Cleaning Sa2.5
RD ___E   5 M2 Blast Cleaning Sa3
           
RD ____*   5   Paint Material
RD ____1   5 M2 Alkyd
RD ____2   5 M2 Chloor Rubber
RD ____3   5 M2 Epoxy
RD ____4   5 M2 High Built Epoxy
           
RD _____*   5   Application Method
RD _____1   5 M2 Brushing
RD _____2   5 M2 Spraying
           
RD   ___*** 6   Layer Thickness (micron)
RD   ___... 6 M2 - any number -