J - Foundations
Stem sub | Rest | Detail | Level | UoM | Description |
---|---|---|---|---|---|
J | 1 | M3 | Foundations | ||
J* | 2 | Foundation Group | |||
JJ | 2 | M3 | Equipment & Structure Foundations | ||
JB | 2 | M3 | Building Foundations | ||
JC | 2 | M3 | Concrete Sewer & Firewater Pits | ||
JE | 2 | M3 | Civil Work Electr. & Instrum. | ||
JP | 2 | M2 | Paving | ||
JL | 2 | EA | Piling | ||
JM | 2 | M3 | Earthwork | ||
JG | 2 | M3 | Grouting | ||
JJ | * | 3 | Foundation Function | ||
JJ | ** | 4 | Foundation Function Details | ||
JJ | A | 3 | M3 | Equipment Foundation | |
JJ | A1 | 4 | M3 | Towers & Vertical Vessels | |
JJ | A2 | 4 | M3 | Horizontal Vessels & Exchangers | |
JJ | A3 | 4 | M3 | Pumps | |
JJ | A4 | 4 | M3 | Compressors | |
JJ | A5 | 4 | M3 | Fired Equipment & /Package Units | |
JJ | A6 | 4 | M3 | Storage Tanks | |
JJ | A7 | 4 | M3 | Miscellaneous Items | |
JJ | D | 3 | M3 | Structure Foundation | |
JJ | D1 | 4 | M3 | Equipment Supporting Structures | |
JJ | D2 | 4 | M3 | Pipe Supporting Structures | |
JJ | D3 | 4 | M3 | Sheds | |
JJ | D4 | 4 | M3 | Noise Walls | |
JJ | __* | 5 | Construction Component | ||
JJ | __*** | 6 | Construction Component Details | ||
JJ | __1 | 5 | M3 | Concrete | |
JJ | __11 | 6 | M3 | Concrete | |
JJ | __12 | 6 | M3 | Blinding | |
JJ | __13 | 6 | M2 | Formwork | |
JJ | __14 | 6 | KG | Bolts | |
JJ | __15 | 6 | KG | Inserts | |
JJ | __2 | 5 | KG | Rebar | |
JJ | __21 | 6 | KG | Mild Steel Bars | |
JJ | __22 | 6 | KG | High Tensile Steel Bars | |
JJ | __23 | 6 | KG | Wire Meshes | |
JJ | __3 | 5 | EA | Prefabrication | |
JJ | __5 | 5 | EA | Coating & Linings | |
JJ | __51 | 6 | EA | Asphalt Coating | |
JJ | __52 | 6 | EA | Acid Resistant Lining | |
JJ | __9 | 5 | EA | Foundation Modifications | |
JJ | __91 | 6 | M3 | Break-up/Removal | |
JJ | __92 | 6 | M2 | Surface Preparation | |
JJ | __92A | 6 | M2 | Chipping-off | |
JJ | __92B | 6 | M2 | Roughening | |
JJ | __92Z | 6 | M2 | Other | |
JJ | __93 | 6 | EA | Anchor Installation | |
JJ | __93A | 6 | EA | Drilling Holes | |
JJ | __93B | 6 | EA | Grout-in Achor Bars | |
JJ | __93C | 6 | EA | Fixing Dowel Bar | |
JJ | __93 | ** | 10 | EA | Size Depth cm |
JJ | __93 | .. | 10 | EA | - Any Number - |
JJ | __93 | ___*** | 14 | EA | Size Diameter mm |
JJ | __93 | ___... | 14 | EA | - Any Number - |
Stem sub | Rest | Detail | Level | UoM | Description |
---|---|---|---|---|---|
JB | * | 3 | M3 | Building Group | |
JB | ** | 4 | M3 | Building Function | |
JB | A | 3 | M3 | Administration Buildings | |
JB | A1 | 4 | M3 | Office Buildings | |
JB | A2 | 4 | M3 | Laboratory Buildings | |
JB | A3 | 4 | M3 | Change Houses | |
JB | A4 | 4 | M3 | General Purpose Buildings | |
JB | E | 3 | M3 | Electrical Buildings | |
JB | E1 | 4 | M3 | Main Stations | |
JB | E2 | 4 | M3 | Substations | |
JB | E3 | 4 | M3 | Emergency Generator Buildings | |
JB | F | 3 | M3 | Service Buildings | |
JB | F1 | 4 | M3 | Fire Stations | |
JB | F2 | 4 | M3 | Garages | |
JB | F3 | 4 | M3 | Truck Loading Offices | |
JB | F4 | 4 | M3 | Weigh Houses | |
JB | F5 | 4 | M3 | Guard Houses | |
JB | G | 3 | M3 | Process Buildings | |
JB | G1 | 4 | M3 | Process Buildings | |
JB | K | 3 | M3 | Control System Buildings | |
JB | K1 | 4 | M3 | Control Buildings | |
JB | K2 | 4 | M3 | Analyser Houses | |
JB | M | 3 | M3 | Maintenance Buildings | |
JB | M1 | 4 | M3 | Maintenance Buildings | |
JB | P | 3 | M3 | Pump & Compressor Houses | |
JB | P1 | 4 | M3 | Compressor Sheds | |
JB | P2 | 4 | M3 | Firewater Pump Houses | |
JB | P3 | 4 | M3 | Pump Houses | |
JB | P4 | 4 | M3 | Boiler Houses | |
JB | S | 3 | M3 | Storage Buildings & Warehouses | |
JB | S1 | 4 | M3 | Storage Buildings | |
JB | S2 | 4 | M3 | Warehouses | |
JB | __* | 5 | Construction Component | ||
JB | __** | 6 | Construction Component Details | ||
JB | __1 | 5 | M3 | Concrete | |
JB | __11 | 6 | M3 | Concrete | |
JB | __12 | 6 | M3 | Blinding | |
JB | __13 | 6 | M2 | Formwork | |
JB | __14 | 6 | KG | Bolts | |
JB | __15 | 6 | KG | Inserts | |
JB | __2 | 5 | KG | Rebar | |
JB | __21 | 6 | KG | Mild Steel Bars | |
JB | __22 | 6 | KG | High Tensile Steel Bars | |
JB | __23 | 6 | KG | Wire Meshes | |
JB | __3 | 5 | EA | Prefabrication |
Stem sub | Rest | Detail | Level | UoM | Description |
---|---|---|---|---|---|
JC | * | 3 | System Function | ||
JC | F | 3 | M3 | Firefighting Systems | |
JC | Q | 3 | M3 | Sewer Systems | |
JC | _* | 4 | Item Type | ||
JC | _1 | 4 | M3 | Manholes | |
JC | _2 | 4 | M3 | Catchbasins | |
JC | _3 | 4 | M3 | Valve Pits | |
JC | _4 | 4 | M3 | Sump Pits | |
JC | _5 | 4 | M3 | Foundation Slabs | |
JC | _6 | 4 | M3 | Anchor Blocks | |
JC | _7 | 4 | M3 | Concrete Bedding | |
JC | _8 | 4 | M3 | Clean-outs | |
JC | _9 | 4 | M3 | Gutters | |
JC | __* | 5 | Construction Component | ||
JC | __** | 6 | Construction Component Details | ||
JC | __1 | 5 | M3 | Concrete | |
JC | __11 | 6 | M3 | Concrete | |
JC | __12 | 6 | M3 | Blinding | |
JC | __13 | 6 | M2 | Formwork | |
JC | __14 | 6 | KG | Bolts | |
JC | __15 | 6 | KG | Inserts | |
JC | __2 | 5 | KG | Rebar | |
JC | __21 | 6 | KG | Mild Steel Bars | |
JC | __22 | 6 | KG | High Tensile Steel Bars | |
JC | __23 | 6 | KG | Wire Meshes | |
JC | __3 | 5 | EA | Prefabrication | |
JC | __31 | 6 | M3 | 0- 5 m3 Pit volume | |
JC | __32 | 6 | M3 | 5-10 m3 Pit volume | |
JC | __33 | 6 | M3 | 10-20 m3 Pit volume | |
JC | __34 | 6 | M3 | > 20 m3 Pit volume | |
JC | __4 | 5 | EA | Covers | |
JC | __41 | 6 | EA | Cast Iron Cover | |
JC | __42 | 6 | EA | Grating Cover | |
JC | __5 | 5 | EA | Coating & Linings | |
JC | __51 | 6 | EA | Asphalt Coating | |
JC | __52 | 6 | EA | Acid Resistant Lining | |
JE | * | 3 | Civil Work Function | ||
JE | E | 3 | M3 | Civil Work for Electrical | |
JE | K | 3 | M3 | Civil Work for Instrumentation | |
JE | _* | 4 | Item Type | ||
JE | _1 | 4 | M2 | Cable Protection Tiles | |
JE | _2 | 4 | M2 | Cable Trench Walls | |
JE | _3 | 4 | M | Conduits | |
JE | _4 | 4 | M3 | Cable Pulling Boxes | |
JE | _5 | 4 | M3 | Formstones | |
JE | _6 | 4 | M3 | Cable Gutters | |
JE | _7 | 4 | M3 | Road Crossing Channels | |
JE | _8 | 4 | M3 | Embedded PVC Conduit | |
JE | __* | 5 | Construction Component | ||
JE | __** | 6 | Construction Component Details |
Stem sub | Rest | Detail | Level | UoM | Description |
---|---|---|---|---|---|
JE | __1 | 5 | M3 | Concrete | |
JE | __11 | 6 | M3 | Concrete | |
JE | __12 | 6 | M3 | Blinding | |
JE | __13 | 6 | M2 | Formwork | |
JE | __14 | 6 | KG | Bolts | |
JE | __15 | 6 | KG | Inserts | |
JE | __2 | 5 | KG | Rebar | |
JE | __21 | 6 | KG | Mild Steel Bars | |
JE | __22 | 6 | KG | High Tensile Steel Bars | |
JE | __23 | 6 | KG | Wire Meshes | |
JE | __3 | 5 | EA | Prefabrication | |
JP | * | 3 | Paving Type | ||
JP | ** | 4 | Paving Component | ||
JP | A | 3 | M2 | Asphalt Paving | |
JP | A1 | 4 | M2 | Sub Base | |
JP | A2 | 4 | M2 | Base Course | |
JP | A3 | 4 | M2 | Wearing Course | |
JP | A4 | 4 | M2 | Top Layer | |
JP | B | 3 | M2 | Brick Paving | |
JP | B1 | 4 | M2 | Concrete | |
JP | B2 | 4 | M2 | Clay | |
JP | C | 3 | M2 | Concrete Paving | |
JP | C1 | 4 | M2 | Slabs | |
JP | C2 | 4 | M3 | Curbs | |
JP | C3 | 4 | M3 | Downstands | |
JP | C4 | 4 | M3 | Plinths | |
JP | C5 | 4 | M2 | Wire Meshes | |
JP | C6 | 4 | M | Joints | |
JP | C7 | 4 | M2 | Coloured Concrete | |
JP | G | 3 | M2 | Gravel Paving | |
JP | G1 | 4 | M2 | Gravel Paving | |
JP | G2 | 4 | M2 | Crushed Stone Paving | |
JP | G3 | 4 | M2 | Slags Paving | |
JP | T | 3 | M2 | Tiles | |
JP | T1 | 4 | M2 | Concrete Tiles | |
JP | T2 | 4 | M2 | Ceramic Tiles | |
JP | T3 | 4 | M2 | Stelcon(type) Slabs | |
JP | *** | 5 | Paving Thickness (mm) | ||
JP | ... | 5 | - any number - | ||
JL | * | 3 | EA | Pile Type | |
JL | F | 3 | EA | Fabricated In-Situ | |
JL | S | 3 | EA | Prefabricated | |
JL | _* | 4 | Pile Type Details | ||
JL | _1 | 4 | EA | Reinforced | |
JL | _2 | 4 | EA | Prestressed | |
JL | _3 | 4 | EA | Bored | |
JL | _4 | 4 | EA | Driven Temporary Casing | |
JL | _5 | 4 | EA | Driven Permanent Casing | |
JL | _6 | 4 | EA | Composite | |
JL | _7 | 4 | EA | Wood | |
JL | _8 | 4 | EA | Steel |
Stem sub | Rest | Detail | Level | UoM | Description |
---|---|---|---|---|---|
JL | ___*** | 5 | Bearing Capacity (tonne) | ||
JL | ___... | 5 | EA | - any number - | |
JL | *** | 6 | Pile Length (m) | ||
JL | ... | 6 | EA | - any number - | |
JL | ____** | 7 | Pile Diameter (cm) | ||
JL | ____.. | 7 | EA | - any number - | |
JM | * | 3 | Groundwork Function | ||
JM | C | 3 | M3 | Process Piping | |
JM | E | 3 | M3 | Electrical Cables | |
JM | F | 3 | M3 | Firewater Lines | |
JM | J | 3 | M3 | Foundations | |
JM | K | 3 | M3 | Instrumentation Cables | |
JM | Q | 3 | M3 | Sewers | |
JM | _* | 4 | Groundwork Type | ||
JM | _1 | 4 | M3 | Excavation | |
JM | _2 | 4 | M3 | Backfilling | |
JM | _3 | 4 | M3 | Transportion | |
JM | _4 | 4 | LT | Dewatering | |
JM | _5 | 4 | LT | Planking & Strutting | |
JM | __* | 5 | Execution Method | ||
JM | __H | 5 | M3 | By Hand | |
JM | __M | 5 | M3 | By Machine | |
JG | * | 3 | Grouting Material | ||
JG | A | 3 | M3 | Embeco | |
JG | B | 3 | M3 | Epoxy | |
JG | C | 3 | M3 | Sand-Cement |