Table of Contents

  1. Purpose
  2. General
  3. Responsibilities
  4. Procedure
  5. Flowchart
  6. References
  7. Attachments

1. Purpose

The purpose of this procedure is to provide a standard for those engaged in the preparation of a mechanical catalogue.

2. General

If a contract calls for the preparation of a mechanical catalogue as part of Company scope of work, then this procedure shall be followed.

On projects where the Client requires an abbreviated type of record/design book or the Client does not require a mechanical catalogue to be supplied, the Company Project History Report could be extended to include all information for Company reference (ref. 6.5), if required. This is to be decided by the Project Manager at the start of a project.

This procedure addresses the standard mechanical catalogue normally produced by Company.

This procedure does not address specific requirements of individual clients which occasionally require less than Company normally produces (e.g. Design Book, ref. 6.4) or more than Company normally produces (e.g. Operating Manual, containing process data).

3. Responsibilities

Ultimately, the Project Manager is responsible for the initiation and compilation of a mechanical catalogue in accordance with the requirements of the client and as stipulated in this procedure.

Generally, the Project Clerk will be designated to compile the mechanical catalogue, when necessary assisted by extra manpower.

The Vendor Print Supervisor shall supply those documents requested, to be included in the mechanical catalogue.

4. Procedure

4.1 Initial Preparation

Immediately following the award of a contract, the Project Manager shall clarify the Client's requirements in regard to a mechanical catalogue.

The Project Manager shall submit to the Client, for their approval or comment, the details of the proposed compilation of the catalogue as outlined in this procedure. Additions and/or deletions shall be clarified at this time.

Preparatory work on the catalogue, like table of contents and layout, will start upon receipt of the first project documents.

The following lists shall be kept up-to-date at all times:

  • List of specifications

(form BN-UE-167;
see also Attachment 5)

  • List of requisitions

(form BN-UE-168;
see also Attachment 6)

  • List of design and engineering drawings

(form BN-UE-169;
see also Attachment 7)

  • Purchasing status

(form BN-UP-23;
see also Attachment 9)

A schedule for the start of assembling documents and final issue date of the mechanical catalogue shall be agreed with the Client together with required copies to be prepared. One copy shall be reserved for Company archive.

The instruction to begin will be given by the Project Manager.

4.2 Compilation

For single unit projects, the mechanical catalogue shall be prepared following Attachment 1. Each volume of the catalogue shall have a Master Index in front, followed by a complete index only in volume I.

For multiple unit projects, the mechanical catalogue shall be prepared following Attachment 2. The index in volume I will consist of the lists of all Company documents and of vendor documents as far as "common to all units". The indices of the units shall always be inserted immediately before the relevant documents, which means that they can come in front of a volume or somewhere half-way.

The list of units shall proceed the indices of the units.

All documents to be inserted are marked "X" in the column "X = Available in catalogue" on the various lists (ref. Attachments 1 and 2).

Where possible, Company documents shall be photo-reduced to A3 or A4 size. In case this is not feasible, drawings to be folded to correct size and inserted in a plastic envelope.

The complete catalogue shall be transmitted to the Client on a date as specified in the contract.

4.3Vendor Documents

Following Company Vendor Print Control (VPC) system of listing the drawings for approval, it is important that a clear description is given of the drawings and that they show requisition, purchase order and equipment item numbers.

The VPC Supervisor shall make sure that the VPC system shows the correct data so that nobody is left in doubt about the kind of drawings recorded. Furthermore, he shall take care that from the final approved prints, a good quality reproducible is available and endeavor to obtain all Vendor documents in time (about three months before scheduled completion of the project).

VPC start making copies for the catalogue after a request has been received from the Project Engineering Department.

As soon as the first drawings for approval have come through, the Project Clerk shall start preparing lists of suppliers' documents (form BN-UE-170, see also Attachment 8 for a typical example). All units shall have their own listing, by account, on separate sheets.

In addition to drawings, all other important vendor documents, such as instruction manuals, sectional drawings, parts lists and test curves, shall also be shown on these lists. These lists shall be kept up-to-date.

Upon completion of the catalogue all reproducibles of final vendor documents are to be transmitted to the Client if specified in the contract, with proper index and transmittal.

Separately bound vendor data (like operating instruction manuals), which is too bulky for insertion in the regular catalogues, will be identified on the binder, listed in the addenda and sent to the Client as a separate book. One (1) set will be retained by Company and kept with the mechanical catalogues.

4.4 Binders and Tab Cards

Due to the nature of the documents involved and the large quantity of paper, multiple ring binders shall be utilized.

The Supervisor of the Project Clerks shall request that an order be placed by Office Services for the estimated number of binders, tab cards and front sheets. The multi-ring binders will normally be black with gold lettering. For spine and front cover layout see Attachment 10.

The tab (separation) cards shall be white, with preprinted side tabs, either showing Index, Section I, Section II, etc., or titles as mentioned below.

Index

Special Equipment

General

Boilers and Heaters

Common to all Units

Civil

Plot Plans

Instrumentation

Flow Diagrams

Tanks and Drums

Specifications

Insulation

Towers

Pumps & Drivers

Buildings

Compressors

Piping

Sewers

Steel Structures

Painting

Electrical

Site Development

Fire Fighting

S & T Exchangers

 

Air Fins

Final titles shall be decided by the Project Clerk, in good time, before the order is placed to supply the cards.

4.5 The mechanical catalogues shall be reviewed by the Project Manager prior to issue to the Client and Company archives.

5. Flowchart

 

 

6. References

 

Document

Number

Title

Level

6.1

CM-PE-110

Maintaining and Coding of Project Files

2

6.2

CM-PE-111

The Final Disposition of Project Documents

2

6.3

CM-PE-113

Microfilming Project Documents (LATER)

2

6.4

QA-017

Compilation of Design Books

2

6.5

CM-PE-115

Project History Report (LATER)

2

 

 

7. Attachments

a. Mechanical Catalogue Contents (for projects consisting of one unit only)

b. Mechanical Catalogue Contents (for projects consisting of more than one unit)

c. Mechanical Catalogue Master Index

d. Mechanical Catalogue (typical List of Units)

e. List of Specifications (typical example)

f. List of Requisitions (typical example)

g. List of Design and Engineering Drawings (typical example)

h. List of Suppliers' Documents (typical example)

i. Purchasing Status (typical example)

j. Binder Front and Back Cover Layout

 

 

Attachment 1

Sheet 1 of 4

CONTENTS OF MECHANICAL CATALOGUE FOR

PROJECTS CONSISTING OF ONE UNIT ONLY

SUBDIVISION

 

INSERTION OF DOCUMENTSIN CATALOGUE

Master Index:

Listing following subdivisions together with the applicable volume numbers.

Copy of Master Index in front of each volume

 

Index

 
 

General:

Equipment List

Plot Plans

Flow Diagrams

General Specifications

 

Towers

Buildings

Piping

Structures

Electrical

Fire Fighting

Special Equipment

Boilers and Heaters

Civil

Instrumentation

Tanks and Drums

Insulation

Pumps and Drivers

Compressors

Sewers

Painting

Site Development

S & T Exchangers

Air Fins

 

 

 

Attachment 1

Sheet 2 of 4

CONTENTS OF MECHANICAL CATALOGUE FOR

PROJECTS CONSISTING OF ONE UNIT ONLY

SUBDIVISION

KIND OF DOCUMENTS

INSERTION OF DOCUMENTSIN CATALOGUE

Index:

List of Specifications, Requisitions, Design and Engineering Drawings, Supplier Documents, Purchase Orders

Copy of complete Index in volume 1 after Master Index

General

Equipment List

 

Plot Plans

Plot Plans

Lines at Plot Limits

Key Plan

In sequence of list of Company drawings

Flow Diagram

Process, Engineering & Utility

Flow Diagrams, Interc. Lines,

Line Designation Table, Symbols,

Abbreviations etc.

In sequence of list of Company drawings

Specifications

Specifications

In sequence of list of specifications

Towers &Internals

Requisitions, Company drawings,
Main Vendor Drawings. If Company drawings are not available (e.g. trays) all Vendor drawings

Sequence in accordance with:



Equipment List

Buildings

Requisitions, Company Main Layout Drawings of Control House and other important building, Vendor Documents on Heating/Ventilating and Electrical

  1. List of Requisitions
  2. List of Company Drawings
  3. List of Vendor Documents

 

Master Key System

 

Piping

Requisitions, Company Drawings,
Vendor Documents, where required for special items only

  1. List of Requisitions
  2. List of Vendor Documents
  3. List of Company Drawing

Structures

Requisitions

List of Requisitions

Electrical

Requisitions -

Company Drawings
Area Classification with:
Key one-line Diagram
One-Line Diagrams
Wiring Diagrams
Control Schemes
Electrical Panel
Layout

Vendor Documents:Vendor Setting Plan (generators)
Wiring Diagrams
Operating Instructions
Sectional Drawings
Parts Lists

Sequence in accordance

  1. List of Requisitions
  2. List of Vendor Document
  3. List of Company Drawings

 

 

Attachment 1
Sheet 3 of 4

SUBDIVISION

KIND OF DOCUMENTS

INSERTION OF DOCUMENTSIN CATALOGUE

Fire Fighting

Requisitions, incl. Motor Data Sheets

Vendor Documents:Setting Plan
Test Curve
Operating Instructions
Sectional Drawings
Parts Lists

  1. List of Requisitions
  2. List of Vendor Documents

SpecialEquipment

Requisitions, incl. Motor and Equipment List
Engineering Data Sheets

Vendor Documents:On Pressure Vessels, Exchangers,
Pumps, Compressors and Agitators

Test Curves
Operating Instructions
Sectional Drawings
Parts Lists

Equipment list

Boilers & Heaters

Company Requisitions, incl.
Engineering Data Sheets

Vendor Documents:General Furnace Layout
General Tube Arrangement
Furnace Controls
Operating Instruc. )
Sectional Drawings ) on burners only
Part Lists )

Equipment list

Civil

Company Requisitions
Foundation Location Plan

Sequence in accordance with:

  1. List of Requisitions
  2. List of Company Drawings

Instrumentation

Requisitions
Instrument Data Sheet
Company or Vendor Wiring Diagrams and Control Panel or Desk Layout

Vendor Documents:Operating Instructions
Sectional Drawings
Parts Lists

  1. List of Requisitions
  2. List of Vendor Drawings
  3. List of Company Drawings

Tanks & Drivers

As for Towers

Equipment List

Insulation

Tables

List of Company Drawings

 

 

Attachment 1
Sheet 4 of 4

SUBDIVISION

KIND OF DOCUMENTS

INSERTION OF DOCUMENTSIN CATALOGUE

Pumps & Drivers

Requisitions, incl., Pumps & Drivers Data Sheets

Vendor Documents:General Arrangement (setting plan)
Mechanical Seal Drawing
Test Curve
Operating Instructions
Sect. Drwg and Parts List

Equipment List

Compressors

As for Pumps. Moreover information on auxiliary equipment (pulsation bottles, coolers, exchangers etc).

Equipment List

Sewers

Requisitions, Schematic Sewer Layouts, Line Tables

  1. List of Requisitions
  2. List of Company Drawings

Painting

Tables

List of Company Drawings

S & TExchangers

As for Towers Equipment List

 

Air Fins

Requisitions, incl. Engineering and Motor Data Sheets with:

Vendor:Setting Plan
Assembly Drawing
Tube Layout
Material List
Gaskets
Operating Instructions
Sectional Drawings
Parts Lists

Sequence in accordance with:

Equipment Lists

 

 

Attachment 2
Sheet 1 of 1

CONTENTS OF MECHANICAL CATALOGUE FOR

PROJECTS CONSISTING OF MORE THAN ONE UNIT ONLY

SUBDIVISION

KIND OF DOCUMENTS

INSERTION OF DOCUMENTS IN CATALOGUE

As Attachment 1 with the addition of "Common to All Units"

As Attachment 1

Common to all units

Shall Cover:Overall Plot Plans
General Specifications
Interc. Diagrams
Service Buildings
Interc. Piping
Structures (interc. Piperacks)
Electrical Distribution
Fire Fighting
Civil (Roads, Fencing, Paving etc.)
Instrumentation
Insulation
Sewers and Drains
Painting
Site Development

Master Index in front of each volume. In Volume 1 followed by the Index, consisting of all lists of Company Documents (see Attachment 1) and as to Vendor Documents “Common to all Units" only.

The indices of the Units will be inserted immediately before the relevant documents so they might be in front of a volume or some where halfway.

For the rest, the insertion of documents shall be in accordance with Attachment 1, with the understanding that "Common to all Units" documents shall be inserted to commence in Volume 1, after the index.

 

 

Attachment 3

Sheet 1 of 1

(CLIENT)

(PROJECT)

(LOCATION)

MECHANICAL CATALOGUE

COMPANY

MASTER INDEX

 

DESCRIPTION

VOLUME

Index :

List of Specifications
List of Requisitions
List of Company Design Drawings
List of Vendor Documents

 

1

(Common to all Units)

General :

Equipment List
Plot Plans
Flow Diagrams
General Specifications

 

Towers
Buildings
Piping
Structural Specifications
Electrical
Fire Fighting
Special Equipment
Boilers and Heaters
Civil
Instrumentation
Tanks and Drums
Insulation
Pumps and Drivers
Compressors
Sewers and Drains
Painting
Site Development
S and T Exchangers
Air Fins

   

Note: To make certain that a document you are looking for is available, please first consult the indices. All documents inserted are indicated by an "X" in the column, "X = available in catalogue".

 

 

Attachment 4
Sheet 1 of 1

LIST OF UNITS

   

UNIT

TITLE

VOLUME

1000

Utilities

 

1100

Oxychlorination Reactor Section

 

1200

EDC Recovery Section

 

1300

EDC Purification Section

 

1400

EDC Cracking and Quench Section

 

1500

VCL Recovery and Purification System

 

1600

Direct Chlorination Reactor Section

 

1800

Primary Waste Water Treatment and Gas Incineration Sections

 

1900

Secondary Waste Water Treatment Section

 

2700

EDC and VCL Storage Section

 

3000

Jetty Area

 

 

Attachment 5
Sheet 1 of 1

LIST OF SPECIFICATIONS

(typical example)

 

 

 

 

 

 

Attachment 6
Sheet 1 of 1

LIST OF REQUISITIONS

(typical example)











Attachment 7
Sheet 1 of 1

LIST OF DESIGN AND ENGINEERING DRAWINGS

(typical example)

 

 

 

 

Attachment 8
Sheet 1 of 1

LIST OF SUPPLIERS' DOCUMENTS

(typical example)

 

 

 

 

Attachment 9
Sheet 1 of 1

PURCHASING STATUS

(typical example)

 

 

 

 

Attachment 10
Sheet 1 of 1