S - Site Development

Project Account and Cost Code for Site Development


Stem subRestDetailLevelUoMDescription
S     1 M3 Site Development
           
S*     2   Site Development Group
SE     2 M2 Site Preparation
SD     2 LOT Demolition
SB     2 M3 Bundwalls
SP     2 M2 Roads
SR     2 M Railways
SF     2 M Fences & Gates
ST     2 M2 Tankpads
SL     2 LOT Jetty Piers & Quays
SG     2 M3 Large Basins & Pits
SJ     2 M3 Special Concrete Work
SM     2 M3 Groundwork for SG & SJ
SQ     2 M Ditches
SX     2 LOT Job Clean Up
SY     2 PC Miscellaneous Major Work
SZ     2 M2 Final Site Finishing
           
           
SE *   3   Preparation Function
SE A   3 M2 Site Cleaning
SE B   3 M2 Site Levelling
SE C   3 M3 Soil Improvement
SE D   3 M3 Main Earth Moving
SE E   3 EA Sand Piles
           
SE _*   4   Groundwork Type
SE _1   4 M3 Excavation
SE _2   4 M3 Backfilling
SE _3   4 M3 Transportation
           
SD **   3   Demolishing Item
           
SD B   3 M3 Buildings
SD DC   3 M3 Concrete Structures
SD DS   3 MT Structural Steel
SD F   3 M Firewater Systems
SD J   3 M3 Below Grade Concrete
SD P   3 M2 Paving & Roads
SD Q   3 M Sewer Systems
           
SB *   3   Construction Component
SB **   4   Construction Component Details
           
SB M   3 M3 Sand Body
SB M1   4 M3 Excavation
SB M2   4 M3 Terp Filling (incl.Compaction)
SB M3   4 M3 Backfilling
           
SB P   3 M2 Protective Layers
SB P1   4 M2 Finish Top
SB P2   4 M2 Finish Slopes

Stem subRestDetailLevelUoMDescription
           
SB __*   5 M2 Construction Material Code
SB __A   5 M2 Site Soil
SB __B   5 M2 Clean Sand
SB __C   5 M2 Clay
SB __D   5 M2 Gravel
SB __E   5 M2 Crushed Stone
SB __F   5 M2 Blast Furnace Slags
SB __G   5 M2 Asphalt
SB __H   5 M2 Sand-Bitumen
SB __J   5 M2 Concrete
SB __K   5 M2 Concrete-Asphalt
SB __L   5 M2 Macadam
SB __M   5 M2 Plastic Foil
SB __N   5 M2 Topsoil with Grass
SB __O   5 M2 Selected Fill
           
SB   *** 6   Layer Thickness (mm)
SB   ... 6 M2 - any number -
           
SP *   3   Road Function
SP A   3 M2 Main Road
SP B   3 M2 Plant Road
SP C   3 M2 Security Road
           
SP ___***   4   Road Width (cm)
SP ___...   4 M2 - any number -
           
SP _*   5   Construction Component
SP _1   5 M2 Sub Grade
SP _2   5 M2 Sub Base
SP _3   5 M2 Base Course
SP _4   5 M2 Paving
SP _5   5 M2 Shoulder Base
SP _6   5 M2 Shoulder Finish
           
SP __*   5   Material Code
SP __A   5 M2 Site Soil
SP __B   5 M2 Clean Sand
SP __C   5 M2 Clay
SP __D   5 M2 Gravel
SP __E   5 M2 Crushed Stone
SP __F   5 M2 Blast Furnace Slags
SP __G   5 M2 Asphalt
SP __H   5 M2 Sand-Bitumen
SP __J   5 M2 Concrete
SP __K   5 M2 Concrete-Asphalt
SP __L   5 M2 Macadam
SP __M   5 M2 Plastic Foil
           
SP   *** 7 M2 Layer Thickness (mm)
SP   ... 7 M2 - any number -
           
SR *   3   Track Component
SR A   3 M Straight Track
SR B   3 M Curved Track
SR C   3 PC Switch
SR D   3 PC Buffer
SR E   3 PC Crossing
           
SR _*   4   Construction Component
SR _1   4 M3 Subgrade
SR _2   4 M3 Ballast Bed
SR _3   4 EA Sleepers
SR _4   4 M Rail

Stem subRestDetailLevelUoMDescription
           
SR __*   5 M2 Material Code
SR __A   5 M2 Site Soil
SR __B   5 M2 Clean Sand
SR __C   5 M2 Clay
SR __D   5 M2 Gravel
SR __E   5 M2 Crushed Stone
SR __F   5 M2 Blast Furnace Slags
SR __G   5 M2 Asphalt
SR __H   5 M2 Sand-Bitumen
SR __J   5 M2 Concrete
SR __K   5 M2 Concrete-Asphalt
SR __L   5 M2 Macadam
SR __M   5 M2 Plastic Foil
SR __1   5 M2 Carbon Steel
           
SR __* *** 6   Layer Thickness (mm)
SR __1 ... 6 M2 - any number -
SR __2 ... 6 M2 - any number -
SR __3 ... 6 M2  
SR __4 ... 6 M2  
           
SF *   3   Fence Component
SF **   4   Component Type
           
SF F   3 M Fence
SF FB   4 M Bars
SF FC   4 M Chain Linked
           
SF G   3 PC Gate
SF GB   4 PC Barrier
SF GR   4 PC Rolling/Sliding
SF GS   4 PC Swing
SF GT   4 PC Tilting
           
SF * **** 5   Height/Width (cm)
SF F .... 5 M - any number -
SF G .... 5 PC - any number -
           
SF *_*       Type Details
SF F_*   6 M  
           
SF G_1   6 PC Single
SF G_2   6 PC Double
           
SF *__*   7   Operation Method
           
SF F   7 M  
           
SF G__H   7 PC Manual Operated
SF G__M   7 PC Motor Operated
           
ST *   3   Construction Component
ST **   4   Component Details
           
ST J   3 M3 Concrete
ST J1   4 M3 Foundation Ring
ST J2   4 M3 Anchor Slabs
ST J3   4 M3 Bottom Drain Pits
           
ST M   3 M3 Groundwork
ST M1   4 M3 Excavation
ST M2   4 M3 Terp Filling (incl.Compaction)
ST M3   4 M3 Backfilling

Stem subRestDetailLevelUoMDescription
           
ST P   3 M2 Finishing
ST P1   4 M2 Finish Top
ST P2   4 M2 Finish Shoulders
           
ST *_*   5   Construction Component
ST *_**   6   Construction Component Details
           
ST J_1   5 M3 Concrete
ST J_11   6 M3 Concrete
ST J_12   6 M3 Blinding
ST J_13   6 M2 Formwork
ST J_14   6 KG Bolts
ST J_15   6 KG Inserts
           
ST J_2   5 KG Rebar
ST J_21   6 KG Mild Steel Bars
ST J_22   6 KG High Tensile Steel Bars
ST J_23   6 KG Wire Mesh
           
ST J_3   5 EA Prefabrication
           
ST M   5 KG  
ST M   6 KG  
ST P   5 KG  
ST P   6 KG  
           
ST ____*   7   Material Code
ST J   7 M2  
ST M   7 M2  
           
ST P___A   7 M2 Site Soil
ST P___B   7 M2 Clean Sand
ST P___C   7 M2 Clay
ST P___D   7 M2 Gravel
ST P___E   7 M2 Crushed Stone
ST P___F   7 M2 Blast Furnace Slags
ST P___G   7 M2 Asphalt
ST P___H   7 M2 Sand-Bitumen
ST P___J   7 M2 Concrete
ST P___K   7 M2 Concrete-Asphalt
ST P___L   7 M2 Macadam
ST P___M   7 M2 Plastic Foil
ST P___O   7 M2 Selected Material
           
ST P *** 8   Layer Thickness (mm)
ST F   8 M2  
ST M   8 M2  
ST P ... 8 M2 - any code -
           
SL *   3   Component
SL A   3 KG Jetty Piers
SL B   3 KG Quays
           
SL _*   4   Component Details
SL _F   4 LOT Firefighting
SL _J   4 M3 Concrete Work
SL _L   4 EA Piling
SL _M   4 M3 Groundwork
SL _Q   4 M Sewers
SL _S   4 KG Steel Work

Stem subRestDetailLevelUoMDescription
           
SG *   3   Basin Group
SG **   4   Basin Type
           
SG A   3 M3 Utility Service Basins
SG A1   4 M3 Cooling Tower Basins
SG A2   4 M3 Fire Water Holding Basins
           
SG B   3 M3 Effluent Treatment Basins
SG B1   4 M3 API Separator Basins
SG B2   4 M3 TPI Separator Basins
SG B3   4 M3 Flotation Basins
SG B4   4 M3 Flocculation Basins
SG B5   4 M3 Sludge Pits
SG B6   4 M3 Neutralization Basins
           
SG C   3 M3 Process Service Basins
SG C1   4 M3 Sulphur Pits
           
SG __*   5   Construction Component
SG __**   6   Construction Component Details
           
SG __1   5 M3 Concrete
SG __11   6 M3 Concrete
SG __12   6 M3 Blinding
SG __13   6 M2 Formwork
SG __14   6 KG Bolts
SG __15   6 KG Inserts
SG __16   6 M2 Lining
           
SG __2   5 KG Rebar
SG __21   6 KG Mild Steel Bars
SG __22   6 KG High Tensile Steel Bars
SG __23   6 KG Wire Meshes
           
SG __3   5 EA Prefabrication
           
SG __4   5 EA Miscellaneous Steel Items
           
SJ *   3   Work Group
SJ **   4   Work Details
           
SJ A   3 M3 Large Items
SJ A1   4 M3 Road Crossings
SJ A2   4 M3 Firewalls
SJ A3   4 M3 Concrete Bundwalls
SJ A4   4 M3 Culverts
SJ A5   4 M3 Retaining Walls
           
SJ B   3 M3 Small Items
SJ B1   4 M3 Sleepers
SJ B2   4 M3 Bund Wall Steps
SJ B3   4 M3 Pipe Bridge Steps
SJ B4   4 M3 Anchor Blocks
SJ B5   4 M3 Hydrant Pads
SJ B6   4 M3 Ladder Pads
           
SJ C   3 EA Pile Cutting
SJ C1   4 EA Cut-off 0 -1.5 M
SJ C2   4 EA Cut-off 1.5-2.5 M
SJ C3   4 EA Cut-off 2.5-5.0 M

Stem subRestDetailLevelUoMDescription
           
SJ   *** 5   Pile Diameter (cm)
SJ A   5    
SJ B   5    
           
SJ C ... 5   - any number -
SJ __*   6   Construction Component
SJ __**   7   Construction Component Details
           
SJ __1   6 M3 Concrete
SJ __11   7 M3 Concrete
SJ __12   7 M3 Blinding
SJ __13   7 M2 Formwork
SJ __14   7 KG Bolts
SJ __15   7 KG Inserts
           
SJ __2   6 KG Rebar
SJ __21   7 KG Mild Steel Bars
SJ __22   7 KG High Tensile Steel Bars
SJ __23   7 KG Wire Mesh
           
SJ __3   6 EA Prefabrication
           
SJ __4   6 EA Miscellaneous Steel Items
           
SM *   3   Groundwork Group
SM G   3 M3 Large basins
SM J   3 M3 Special Concrete Work
           
SM _*   4   Groundwork Type
SM _**   5   Groundwork Type Detail
           
SM _1   4 M3 Excavation
SM _1H   5 M3 By Hand
SM _1M   5 M3 By Machine
           
SM _2   4 M3 Backfill
SM _2H   5 M3 By Hand
SM _2M   5 M3 By Machine
           
SM _3   4 M3 Transport
SM _3A   5 M3 Inside Battery Limit
SM _3B   5 M3 Outside Battery Limit
           
SM _4   4 LOT Dewatering
SM _4A   5 LOT Open Pumping
SM _4B   5 LOT Well Pointing
SM _4C   5 LOT Deepwell Pumping
           
SM _5   4 LOT Planking & Strutting
           
SM _6   4 M2 Sheet Piling
SM _6P   5 M2 Permanent
SM _6T   5 M2 Temporary

Stem subRestDetailLevelUoMDescription
           
SM _7   4 M3 Filling
SM _7A   5 M2 Site Soil
SM _7B   5 M2 Clean Sand
SM _7C   5 M2 Clay
SM _7D   5 M2 Gravel
SM _7E   5 M2 Crushed Stone
SM _7F   5 M2 Blast Furnace Slags
SM _7G   5 M2 Asphalt
SM _7H   5 M2 Sand-Bitumen
SM _7J   5 M2 Concrete
SM _7K   5 M2 Concrete-Asphalt
SM _7L   5 M2 Macadam
SM _7M   5 M2 Plastic Foil
           
SQ *   3   Work Type
SQ **   4   Work Details
           
SQ M   3 M3 Groundwork
SQ M1   4 M3 Excavation
SQ M3   4 M3 Transport
SQ M4   4 M3 Dewatering
           
SQ P   3 M2 Lining
SQ P1   4 M2 Finish Bottom
SQ P2   4 M2 Finish Slopes
           
SQ *_*   5   Construction Material Code
           
SQ M   5 M2  
           
SQ P_A   5 M2 Soil from Site
SQ P_B   5 M2 Clean Sand
SQ P_C   5 M2 Clay
SQ P_D   5 M2 Gravel
SQ P_E   5 M2 Crushed Stone
SQ P_F   5 M2 Blast Furnace Slags
SQ P_G   5 M2 Asphalt
SQ P_H   5 M2 Sand-Bitumen
SQ P_J   5 M2 Concrete
SQ P_K   5 M2 Concrete-Asphalt
SQ P_L   5 M2 Macadam
SQ P_M   5 M2 Plastic Foil
           
SQ * *** 6   Layer Thickness (mm)
SQ M   6 M2  
SQ P ... 6 M2 - any number -
           
SY *   3   Work Type
SY A   3 M3 Bridges
SY B   3 M3 Viaducts
SY C   3 M3 Hydraulic Filling
           
SZ *   3   Work Type
SZ A   3 M2 Levelling
SZ B   3 M2 Layer Finishing
SZ C   3 M2 Landscaping